|
After the charrette meetings on June
10th and 13th the Design Team used the Town
Center Project Goals,
Lessons Learned, and scheme ideas from Charrette Work Session 3
to create three draft designs for the Conceptual Master Plan. On
June 30th the Town Council held a special session to review the
draft designs, with approximately 80 people attending the meeting. The
Design Team presented the draft designs, citing the features, pros,
and cons of each. The public was then invited to comment on each
design; approximately 45 spoke and 12 turned in written comments,
mostly in support of scheme B but not exclusively. After the discussion
was concluded the Town Council deliberated and instructed the Design
Team to further develop schemes B and C, and present back to the
community and Town Council in September. The draft plans discussed
at the 6/30/04 session, public discussion, and written comments
are documented below.
 |
|
Buildings |
Approx. 26,500 sq. ft. |
|
Fields/Courts |
New relocated Baseball & Soccer Fields,
three new Courts |
|
Parkland |
2.1 acres |
|
Access |
No road through site.
Primary access from south drive. |
|
Parking |
107 spaces total
65 at Town Center & South Drive
42 at School House |
|
Creek |
Adjacent to Town Center and Baseball |
|
Maintenance Facility |
Located on South Drive with Town Center |
|
Preliminary Cost |
$15 million |
|
Phase I |
Library, Town Hall, Maintenance Facility, Creek, some parking. No soccer in Phase I. |
|
Phase II |
Community Hall, Pre-School, Playground, Courts and parking.
|
|
| Adjacencies |
Buildings have connection
to creek |
| Access/Parking |
Roads at Periphery |
| Fields |
Two new fields |
| Solar Access |
Buildings have good solar
access |
|
|
Adjacencies |
Maintenance Facility at entry to Town Center |
|
Access/Parking |
Increased traffic on South Dr. |
|
Fields |
Expense of two new fields |
|
Conservation |
Impacts most of site |
|
Creek |
Requires complete restoration of existing creek |
|
| While it was not the preferred scheme of most people attending
the charrette, participants did find aspects of this scheme appealing – they
liked the openness at the front of the site and the safety afforded
by keeping all the vehicles to the periphery. While parking within
the Town Center cluster was seen as a benefit, some expressed
concern that both the drive along the south side of the property
and the parking lot within Town Center would be too congested.
To some, the library, town hall and classroom activities felt
too concentrated, being hemmed in between the creek on one side and
the maintenance facility on another. The Schoolhouse, on the
other hand, was isolated at the front of the site. People also
expressed concern that the row of buildings and fences at the
back of the site would create a wall that would block the views
of the orchard and western hills. |
 |
|
Buildings |
Approx. 26,500 sq. ft. |
|
Fields/Courts |
New relocated Baseball Field,
Upgraded Soccer Field, three new Courts |
|
Parkland |
3.25 acres |
|
Access |
No road through site.
Access from Portola Rd and south drive. |
|
Parking |
122 spaces total
44 at Courts, 14 at Maintenance Facility,
26 at Town Center, 14 at School House,
24 at new access road |
|
Creek |
Adjacent to Parkland and Town Center |
|
Maintenance Facility |
Located on south drive separate from Town Center |
|
Preliminary Cost |
$14 million |
|
Phase I |
Library, Town Hall, Maintenance, access road, some parking. No Courts or Baseball in Phase I. |
|
Phase II |
Community Hall, Pre-school, Playground, Creek, Courts and parking |
|
|
Adjacencies |
Buildings and Parkland have connection to creek |
|
Access/Parking |
Roads at periphery. Requires increased planting/berming at Portola Road. |
|
Fields |
New baseball field, upgraded Soccer Field |
|
|
Fields |
Tight Soccer Field |
|
Conservation |
Impacts most of site |
|
Solar Access |
Some buildings shaded by redwood grove |
|
Most people who spoke at Work Session 4 expressed
preference for this scheme. The primary benefits noted were:
keeping vehicular traffic to the periphery of the site; tucking
a large portion of the Town Center cluster out of view behind
the Church on the existing tennis courts; maintaining the existing
view corridor through the site from Portola Road towards the
western hills and opening a second one over the baseball field.
An expressed drawback to this scheme was the introduction of
a drive and parking adjacent to Portola Road, and the number
of trees within the existing Town Center that would have to be
removed to accommodate the new baseball field. On the other hand,
people did express support for removing the non-native trees
around the Schoolhouse and other areas of the site.
Open Space
Many liked the new parkland proposed where the existing baseball
field is now. Some wished for greater separation between the
existing oak woodland and the new baseball field, and suggested
narrowing the space between the baseball and soccer field. There
was concern expressed that the tennis and baseball fences would
not be attractive as seen from Portola Road or the south drive.
Creek
Many found the opening of the creek appealing and expressed
interest in seeing it opened further. While others also saw
it as an amenity,
they worried about its safety during storms and wet El Nino
years. One participant felt the creek should not be opened
for reasons
of cost, safety, and the probability of a “designed” creek
bed looking contrived.
Recreation
While many liked the general placement of the recreational
facilities, some offered suggestions on improving their specific
locations
and use. Many did not like the location of the maintenance
facility at the south end of the soccer field for a variety
of reasons – it
shortened the soccer field, balls would fly into the maintenance
yard unless a tall fence or net was provided, there would
be conflict at the parking area between soccer players and
maintenance
traffic. One person suggested moving the maintenance facility
closer to the tennis courts.
Some people were very disappointed that there were only three
dedicated tennis courts in the plan. Others want the MUR to include
a ball court. Acknowledging that this would increase the size
of the MUR, one suggested placing this building along the west
property line along the orchard. Some would like to see a dog
park on this site. Many would like public restrooms located near
the outdoor recreation facilities.
Buildings
Many liked the location of the library away from the recreation
fields and the noise they generate. One person commented that
it would be nice for the library rooms to offer a view of the
creek as in Scheme A. Another noted that there is very little
emphasis on art in this or the other alternatives, and went on
to suggest a small, dedicated art gallery, similar to when the
Schoolhouse was a gallery.
Parking/Circulation
While many liked the concept of keeping parking and circulation
at the edge of the new parkland near Portola Road, many had comments
on how this parking could be improved. One suggested the parking
surface be gravel and not paved. Others would like to eliminate
or minimize the parking at that location or move it to the other
side of the new drive to not obscure the views of the western
hills. Individuals also expressed concern that the plan did not
provide adequate parking for the library and the playing fields.
A U-shaped drive close to the buildings was suggested to facilitate
pick-up and drop-off, which many felt was not realistically addressed
in this or any alternative. It was also suggested that the parking
at the tennis courts be connected via a new drive to the existing
Town Center entrance. Some wondered if the neighboring church
would be willing to either provide access or share parking with
the Town, two ideas which have to be taken up with the church.
|
 |
|
Buildings |
Approx. 26,500 sq. ft. |
|
Fields/Courts |
Existing Baseball Field,
Upgraded Soccer Field, three new Courts |
|
Parkland |
3.25 acres |
|
Access |
Road through site south of Baseball Field.
Access from Portola Rd and south drive. |
|
Parking |
115 spaces total
48 at Courts, 13 at Maintenance Facility,
27 at Town Center, 27 at School House. |
|
Creek |
Adjacent to Parkland and Soccer Field |
|
Maintenance Facility |
Located on south drive separate from Town Center |
|
Preliminary Cost |
$13 million |
|
Phase I |
Library, Town Hall, Maintenance Facility, some parking. No Courts in Phase I. |
|
Phase II |
Com. Hall, Pre-school, Playground, Creek, Courts and parking |
|
|
Adjacencies
|
Parkland is central to site and has connection to creek |
|
Fields |
Upgraded Soccer Field |
|
Conservation |
Retains mature trees, minimizes grading |
|
|
Access/Parking |
Road through site |
|
Fields |
Existing Baseball Field, tight Soccer Field |
|
Solar Access |
Some buildings shaded by Redwood Grove |
|
Open Space
Many participants agreed that there is a greater sense of open
space in this design. They liked this scheme because it protects
the rural quality of the site and fits most closely with
the existing environment. This scheme also has minimum impacts
to the trees and topography because it keeps the playing
fields in place. One participant thought that leaving the
open space undeveloped is great, but it came at the expense
of the safety due to the access road through the site. A
few participants thought that opening the creek was a good
idea, especially if it is kept in a natural area of the site.
Recreation
Several participants thought having the sports fields at separate
sites was good and thought preserving the location of the existing
fields was beneficial. A few participants asked that three tennis
courts be built and that the sport court be located apart from
them, perhaps close to the baseball field. One participant noted
that the baseball field at this size does not support adult activity.
Circulation
Many participants felt that the road through the site would be
dangerous, especially for children. They thought that, for this
plan to work, there must be a way to ensure that people would
be safe crossing the road in the middle of the site. One participant
suggested pulling the baseball field into the site so that the
road can be on the perimeter. Another participant recommended
putting speed bumps on the road and installing fences along the
side of the road. Still another suggested diverting the stream
a bit and moving parking to the back of the site, eliminating
the need for the road through the center of the site. The Design
Team noted that the Redwood Grove at the back of the site prevents
a road from going fully around the back of the site. If parking
were at the Redwood Grove it would not be close enough to the
buildings to comply with fire code regulations. Because a few
participants thought driving into the center of the site was
appealing, one participant thought that lowering the road and
building a pedestrian bridge would make the scheme safer and
get cars out of view. The Design Team was reminded that this
road must accommodate two-way traffic and that people will drop
kids off along the road and then attempt a u-turn, creating a
traffic backup.
Parking
Several participants had suggestions on how to make the parking
more accessible and convenient. One idea was to move the road
behind the soccer field for access and handicapped parking
only, then add more parking behind the old school house and
where the
non-native trees now stand. Another suggestion was to move
the maintenance yard into the easement (if allowed), allowing
space
to shift the soccer field south and allow more space for parking
nearer the buildings. A third idea was to remove the road and
add more parking in the southwest corner of the site because
having a parking lot next to the church would be very noisy.
One participant suggested that the parking spaces closest to
the library be marked with “Please save these spaces for
our senior citizens”.
Buildings
Several suggestions about building phasing and usage were noted.
One participant thought the town center should have offices on
the ground floor rather than the second floor. While most participants
agreed that having the classrooms built in Phase 1 was a good
idea, one noted that having classrooms opening directly onto
a parking lot is dangerous. It was suggested that the science
classroom/nature center be situated to access a native plant
garden and outdoor exploration area, which could also provide
optimal natural light for the classroom as well. One citizen
thought that the idea of building a large multi-use room would
have to be well planned to ensure maximum usage, considering
the large size. Another suggested building four classrooms with
movable walls so they can become the MUR. A request for an adequate
number of accessible bathrooms was noted. Several participants
thought that the pre-school should not be located on public land.
The need for a pre-school was recognized, but many thought it
should be located elsewhere in town.
The Design Team will further develop layout
and ideas presented in Schemes B and C based on input from
the Portola Valley
Community. As part of the Team’s work this summer
they will review the plans with a traffic consultant for
input on circulation, parking and emergency access. The
Team will also work with the Town's maintenance staff to develop
a maintenance facility that meets the maintenance needs
of the Town. In September the Design Team is currently planning to present
the two revised schemes back to the Town of Portola Valley
at two public meetings:
- Town Council on Wednesday 9/8/04 at 7:30 PM in the Multi-Use Room.
- Joint session of the Architectural Site and Control Commission (ASCC) and the Planning Commission on Monday 9/13/04 at 7:00 PM in the Multi-Use Room.
Following the first presentation, revised drawings will
be available in the Library, Town Hall and on the Town Website
for additional review and written public comment.
Based on input at these meetings and written comments from
the community, the design team will prepare the Final Draft
of the Conceptual Master Plan to Town Council on 10/13/04 at 7:30 PM. The Final Conceptual Master Plan will be presented to the Town Council at a Special Session on November 3 at 7:30 PM.
|
|